Barapullah Phase-III Flyover in Delhi Set for Completion by June End
Delhi's Barapullah Phase-III flyover to be ready by end of June: PWD minister

Image: News 18
The Barapullah Phase-III flyover in New Delhi is expected to be completed by June 30, 2023, according to Delhi PWD Minister Parvesh Sahib Singh. This project aims to enhance connectivity between east and south Delhi, featuring a dedicated cycle track for sustainable transport.
- 01The Barapullah Phase-III flyover has been under construction since 2015 and has faced multiple delays and cost escalations.
- 02Initial project costs were estimated at ₹1,260.63 crore, with current expenditures reaching ₹1,238.68 crore, and total completion costs expected to be around ₹1,500 crore.
- 03The flyover will connect Mayur Vihar-I in east Delhi to AIIMS, creating a 9 km signal-free corridor.
- 04For the first time in India, the flyover will include a dedicated cycle track to promote sustainable mobility.
- 05The bridge over the Yamuna floodplain features spans of nearly 125 meters to minimize environmental impact.
Advertisement
In-Article Ad
The Barapullah Phase-III flyover in New Delhi is anticipated to be ready for public use by June 30, 2023, as stated by Delhi's Public Works Department (PWD) Minister Parvesh Sahib Singh. This project, which has been under construction since 2015, aims to provide seamless connectivity between Mayur Vihar-I in east Delhi and AIIMS, covering a distance of approximately 9 km. Originally sanctioned at an estimated cost of ₹1,260.63 crore, the project has already incurred expenses of ₹1,238.68 crore, with total costs projected to reach around ₹1,500 crore. Singh emphasized the government's commitment to overcoming delays and ensuring timely completion, highlighting the flyover's innovative design that includes a dedicated cycle track, promoting greener transportation options. Additionally, the bridge structure over the Yamuna floodplain has been constructed with long spans to minimize environmental disruption, further enhancing the project's significance in urban infrastructure development.
Advertisement
In-Article Ad
The completion of the Barapullah Phase-III flyover will significantly improve traffic flow between east and south Delhi, reducing travel time for commuters.
Advertisement
In-Article Ad
Reader Poll
What do you think about the new Barapullah Phase-III flyover?
Connecting to poll...
More about Public Works Department

Delhi's PWD Implements Green Initiatives for Sustainable Energy
Hindustan Times • May 25, 2026
Nagpur's ₹9 Crore Project Aims to Resolve Waterlogging at Narendra Nagar Underpass
The Times Of India • May 23, 2026

Complaint Filed Against PWD for Alleged Illegal Tree Felling in Shalimar Bagh
Hindustan Times • May 22, 2026
Read the original article
Visit the source for the complete story.